Unexpected Snags Hold Up Railroad Repairs

By: Shawn Magrath

NORWICH – Almost two years after the Chenango County Industrial Development Agency was awarded $4.7 million in federal grants for the restoration of the defunct Utica Main Line, hopes of having repairs to the railroad completed by the end of the year are fading.

The CCIDA (the economic development arm of Commerce Chenango) initially intended to see work done to the railroad as early as this spring. However, in a recent report to the Chenango County Planning and Economic Development Committee, unexpected snags in the project are causing delays, said Commerce Chenango President Steve Craig.

The biggest setback, Craig explained, has been a reoccurring change in staff at the northeast regional offices of the Federal Economic Development Administration (EDA). The EDA committed $4.7 million toward the project in June, 2013. But in the two years since, the Chenango County IDA has dealt with four different EDA reps, two lawyers, and two EDA regional directors.

“All the people who have ushered this project along over the last three years have changed which has caused some confusion,” said Craig, adding that legal issues which were once thought to be resolved have begun to resurface. Such issues include a request by the EDA to obtain a title opinion from every land owner where the 45.5 miles of the Utica Main Line crosses in the county – a process that would stall the project indefinitely and cost a significant amount of money. Craig said concerns over property and ownership were believed to have been resolved last year.

“We are making good progress with the EDA,” he added. “This isn’t going to kill the project. It’s just going to make it take a little longer.”

The CCIDA is also working with the Department of Environmental Conservation on matters regarding waterways around the railroad. According to the DEC, repairs to the railroad may disrupt water flow where rocks and soil have eroded during the nine years the tacks have been inoperable. Craig said he hopes to see that issue resolved soon.

Story Continues Below Adverts

Despite bumps along the way, the CCIDA expects that engineering, including the marking of approximately 17,000 ties in need of replacement, will still be completed by summer.

TO READ THE FULL STORY

The Evening Sun

Continue reading your article with a Premium Evesun Membership

View Membership Options




Comments

Official Evening Sun Facebook

pennysaver logo
Shop4Autos logo
greatgetaways logo
Official Evening Sun Twitter