Supervisors Frustrated By Another Delay In Towers Project

By: Melissa deCordova

Supervisors frustrated by another delay in towers project

NORWICH – Tempers flared Monday when members the Chenango County Board of Supervisors learned that a long-awaited E-911 radio transmission system would be yet another three months late.

The system was scheduled to go live this fall, but with antenna and radio installations remaining at four tower sites and final radio frequency testing expected to carry on through early December, officials are indicating it could be toward the end of the year now.

The $6 million project, in concept, has been underway for more than a decade. Tower installations began with the completion of the county’s new Public Safety Facility in 2007.

The updated emergency communications system replaces three towers constructed in the 1970s that served only 25 percent of the county with nine towers and 98 percent coverage. Frequencies went from four channels to 16. Eventually, all 21 fire departments will be required to purchase new UHF radios in order to be compatible. Thirteen of them have already.

“We’re making every effort we can to improve on this schedule,” said Chenango County Emergency Management Director and Fire Coordinator Matt Beckwith, who presented a project update at this month’s meeting of the county board.

Beckwith pointed to the end of December for a full sign off. “We’re very optimistic that we’ll meet the deadline,” he said.

Story Continues Below Adverts

Supervisors from the towns of Smyrna and Otselic expressed their frustration with a lack of emergency radio coverage as well as the county’s inability to contract with a cellular telephone carrier for the towers.

James B. Bays, D-Smyrna, said his highway and fire responders have been toned out ever since the tower project began, resulting in decreased coverage. Beckwith said he was aware of that situation in Smyrna, saying it was also the situation in Otselic and Sherburne. County EMS officials have resorted to text messaging in order to alert security departments about emergencies in those regions, he said.

David J. Messineo, D-Otselic, said his constituents have been waiting three years for cellular phone coverage. He said he recently learned that the county’s attorney received a draft contract from an AT&T installer back in May of 2009.

“How’s the lease to AT&T coming along?” he asked. “I heard it’s not going so well. I’ve been listening to this (tower project presentations) for three years now. Cell companies co-locate all of the time on towers. You see them working on these towers all over the place. Don’t say we can’t fill in the gaps. The people of Otselic Valley are being held up, not by AT&T, but by our people not being able to complete a contract. You’ve had it since May of 2009. Now this week ... just send it out!”

TO READ THE FULL STORY

The Evening Sun

Continue reading your article with a Premium Evesun Membership

View Membership Options




Comments

Official Evening Sun Facebook

pennysaver logo
Shop4Autos logo
greatgetaways logo
Official Evening Sun Twitter